# Phase 4 Execution Plan
|
|
|
|
Phase 4 milestone: `#3` - AAA SaaS Productization and UX Polish.
|
|
|
|
## Objectives
|
|
|
|
- Move Schemeta from prototype ergonomics to production-grade UX/UI quality.
|
|
- Enforce measurable quality gates for beta and GA releases.
|
|
- Sequence high-risk engine work (layout/routing) behind stable UX foundations.
|
|
|
|
## Workstream Order
|
|
|
|
1. `#23` AAA-00: Plan and quality gates
|
|
2. `#15` AAA-01: Visual system redesign
|
|
3. `#16` AAA-02: Fit-to-view and viewport behavior
|
|
4. `#17` AAA-03: Layout engine v3
|
|
5. `#18` AAA-04: Routing engine v3
|
|
6. `#19` AAA-05: In-canvas editing overhaul
|
|
7. `#20` AAA-06: Diagnostics UX 2.0
|
|
8. `#21` AAA-07: Accessibility/responsive/keyboard pass
|
|
9. `#22` AAA-08: SaaS + MCP production hardening
|
|
|
|
## Dependency Graph
|
|
|
|
- `#15` is prerequisite for high-fidelity baseline updates and consistent UI controls.
|
|
- `#16` depends on `#15` token/layout primitives.
|
|
- `#17` depends on `#16` viewport/fit behavior to evaluate perceived quality.
|
|
- `#18` depends on `#17` placement decisions and semantic lanes.
|
|
- `#19` depends on `#15` and should begin in parallel with late `#17` work where safe.
|
|
- `#20` depends on `#19` interaction model for click-to-fix workflows.
|
|
- `#21` runs continuously but final pass must occur after `#15/#19/#20`.
|
|
- `#22` can run in parallel, but final contract freeze occurs after `#19/#20`.
|
|
|
|
## Critical Path
|
|
|
|
`#15 -> #16 -> #17 -> #18 -> #19 -> #20 -> #21 -> #22`
|
|
|
|
## Risk Register
|
|
|
|
1. Layout/routing regressions on dense circuits.
|
|
- Mitigation: expand fixture corpus, snapshot + metric thresholds, staged rollout.
|
|
2. Visual redesign causing interaction regressions.
|
|
- Mitigation: preserve interaction test suite, baseline review checklist.
|
|
3. Editor complexity inflation.
|
|
- Mitigation: keep single source of truth for selection/edit state, strict undo invariants.
|
|
4. API/MCP compatibility drift.
|
|
- Mitigation: contract tests and explicit schema/api version policy enforcement.
|
|
|
|
## Definition of Done (Phase 4)
|
|
|
|
- All issues `#15-#23` closed with acceptance criteria verified.
|
|
- Release checklist passes all beta and GA quality gates.
|
|
- Browser regression and baseline review pass on representative fixtures (including dense analog).
|
|
- API/MCP contract tests pass with versioned compatibility notes.
|