2.0 KiB
2.0 KiB
Production-Readiness Acceptance Gate
Working plan for Gitea issue
#50.
This gate is broader than the M7 feature list: it proves the complete daily authoring, content,
recovery, performance, and release workflow against one exact release-candidate commit.
Status
Audit in progress. The versioned acceptance matrix exists, but no release candidate is nominated and the gate is not signed off. Packaged/release testing remains explicitly deferred until the project owner requests it again.
Sequence
- Keep one evidence matrix under
docs/editor/evaluations/production-readiness/; historical H1-H6 notes remain context only. - Close implementation blockers before nominating a candidate: collaborative safety
#49, the remaining Material/drag-drop contract in#16,#18, and#51, terrain#22-#24, physics placement/diagnostics#25-#26, and their regression fixtures. - Complete the representative regression project, mutation-invariant coverage, performance budgets,
and first-hour workflow tracked by
#32-#36. - Nominate one exact commit, validate it from a clean checkout, and record source/headless results.
- When packaged testing is re-enabled, run the candidate's package/build and packaged-runtime matrix without substituting older artifacts.
- Run the eight-hour soak and measured performance protocol, consolidate limitations by severity and workaround, and obtain independent first-hour/recovery sign-off.
- Post the signed Gitea milestone comment linking the exact commit and immutable evidence. Close
#50only when every required row passes and no P0 blocker remains.
Gate Rules
- Feature presence is not acceptance evidence.
- A local dirty worktree is not a release candidate.
- Results from another commit or an old package do not transfer to the candidate.
- Deferred, missing, partial, and implementer-only evidence are not passes.
- Every failure records an owner ticket or a concrete rerun condition.